CT Power projet Out

CABINET DECISIONS – 13 MARCH 2015
 
1.         Cabinet has decided not to proceed with the power plant project of the Mauritius CT Power Ltd at Pointe aux Caves taking into consideration the circumstances surrounding the award of contract and the failure of the promoters of the project to submit evidence of their financial capacity or the sources of funding. Government would consider other feasible options, with necessary transparence and clarity, to meet electricity demands for the period 2015-2019 and ensure energy security for Mauritius.
~~~